avi mendelson17 בנוב׳ 2021זמן קריאה 1 דקותHow to add buffer size in ms project as percentage How to add buffer size in ms project Add custom field:Add the custom field:Change the field to formula:Enter the formula:Str(int([Duration]/ProjDateDiff([Current Date],[Finish],[Project Calendar])*100)) & "%"
How to add buffer size in ms project Add custom field:Add the custom field:Change the field to formula:Enter the formula:Str(int([Duration]/ProjDateDiff([Current Date],[Finish],[Project Calendar])*100)) & "%"